*AWS(American welding society Certified Welding Inspector (CWI) (certification no. 05100861)
*AWS(American welding society) membership, member number 551239
*Magnetic particle testing within the recommendation of SNT-TC 1A (1996), level II (two). (M.T)
*Visual testing within the recommendation of SNT-TC 1A (1996), level II (two). (V.T)
*Radiographic testing within the recommendation of SNT-TC 1A (1996), level II (two). (R.T)
*Liquid Penetrant testing within the recommendation of SNT-TC 1A (1996), level II (two). (P.T)
*Ultrasonic testing within the recommendation of SNT-TC 1A (1996), level II (two). (U.T).
Education
B.sc. degree in Metallurgical engineering,
Faculty of petroleum & mining
Engineering, Suez Canal University.
Experience
March 2005 until now _:
Welding inspector& NDT (Client Rep.), R.T interpreting, P.T, V.T, U.T, M.T in Gupco (Suez gulf Petroleum Company), western desert locations Abu El Gharadik (A/G) & Razzak (Rzk) &Alamin through Construction Sector, Supervision & follow up on Contractors Company as (E.M.C) Egyptian maintenance Petroleum Company and (PETROMAINT) Alexandria maintenance Petroleum Company
- pipe line for new shipping line from main rzk to west rzk (6" 10km) ,applicable code: api 1104
- pipe system for fire fighting extension @rzk applicable code: api 1104
- dilution tank 5000bbls repair applicable code: api653
December 2004 up to march 2005_:
Welding& NDT inspector (Client Rep.), interpreting R.T films
Project : Qasr Gas development project, 3 pipe lines (140Km/24", 20", 18"), western desert
Client : Khalda petroleum company (KPC).
Contractor: Petrojet
Applicable code: API 1104
October 2002 to August 2004:
Welding inspector& NDT (Client Rep.), R.T interpreting, P.T, V.T, U.T, M.T in Gupco (Suez gulf Petroleum Company), western desert locations Abu El Gharadik (A/G) & Razzak (Rzk) &Alamin through Construction Sector, Supervision & follow up on Contractors Company as (E.M.C) Egyptian maintenance Petroleum Company and (PETROMAINT) Alexandria maintenance Petroleum Company
- Performing repair internal separator #201Ê @ A/G oil process, Applicable code: API 5070 & ASME VIII
- Reconstruction storage tank(repair) ( 2000 bbl @ A/G 33-15 area, Applicable code: API 653.
- Reconstruction storage tank(repair) Nipco #01 (30000 bbl )&storage tank Nipco #02 (100 000 bbl )@ Alamin area, Applicable code: API 653.
- Piping system of separator # 203 & 204 @ Razzak oil process, Applicable code: ASME B31.3.
- Performing repair internal separator # 201 & #202ËÌ Razzak oil process. Applicable code: API 570& ASME. VIII.
- Performing repair internal heat exchanger @ Razzak oil process, Applicable code: API 570 & ASME VIII.
- Construction 2 skimmers @ Razzak oil process. Applicable code: ASME VIII.
- Piping system for desalter @ Razzak oil process, Applicable code: ASME B31.3.
- Piping system for water disposal project @ Razzak oil Process, Applicable code: ASME B31.3
- Pipe line crude oil (6" / 45 km ) western desert : from well #52 to well #2 , Abuel Gharadik,Applicable code: API 1104.
- Construct 2 tanks fresh water ( 5 000 bbl )@ Abuel Gharadik,Applicable code: API 650.
- Pipe line crude oil (6" / 35 km ) western desert from
well #2 to main manifold, Razzak.
, Applicable code: API 1104.
- piping system for shipping line( 12") @ alamine area, applicable code: api 1104.
- pipe system for new flare line @rzk(12"&10"&8"&6"&4"&3"&2" and1") applicable code: asmeb31.3.
- design and construct fuel net work in alamien area.
-construct 3 shelter with over head crane in each one in A/G gas plant applicable code :aws d1.1
June 2002 up to September 2002:
Welding& NDT inspector (Main contractor Rep.), interpreting R.T films
Client : Burullus gas company
Main contractor: Bechtel intec construction
Sub contractor: Petrojet.
Project: West delta deepmarine concession onshore scaRab saffron development project(30 " / 27 km) pipeline. from burullus to Abo-Hommos.
Applicable cod: API 1104
April 2002 to June 2002:
Welding& NDT inspector (Client Rep.), interpreting R.T films
Client : G .P.C. (The General Petroleum Company)
Contractor :Petrojet,ras-gharib- baker
Project:6" submarine pipeline r/g for offshore platform amer #2 & 7
Applicable code: API 1104
December 2001 up to April 2002:
Welding& NDT inspector (Contractor Rep.), Q.C and Q.A document
Project:Fayum gas development high pressure pipeline (70 Km, 16", 12") and 4 gas plant construction
Client:Fayum Gas Company (F.G.C)
Contractor :Egyptian Maintenance Company (EMC).
Applicable code: API 1104 & ANSI B31.3
August 2001 up to November 2001:
Welding & NDT inspector (Client Rep.), interpreting R.T films
Project: 10" crude oil P/L (9 km) from south Amer to South Baker plant.
Client: G.P.C. (at Ras Ghareb )
Contractor : ECONTO
Applicable code: API 1104
July 2001 up to august 2001:
Welding & NDT inspector (Contractor Rep.), , M.T& P.T
Project:steel structure frames & supports of Edial factory
Client: Edial. (At 10Th of Ramadan)
Contractor:Hassan Alam sons
June 2001 up to July 2001:
Welding & NDT inspector (Client Rep.) , interpreting M.T& P.T
Project:steel structure of management building of artock group
Client:Arab Contractor Company
Location:El-Mokatam
January 2001 up to may 2001:
Welding & NDT inspector (Contractor Rep.), interpreting R.T films
Project:Inspection of affected area from October complex Production Deck & repair storage tank (8000 bbl)
Client:Gupco (RAS SHOKIR OFFSHORE)
Contractor:ECCO
Applicable code:API 653